Conveyor Belt Project

Overview

Conveyor Belt Project

Part 1

Project Description

The new computer-controlled conveyor belt is an exciting project that moves and positions items on the conveyor belt within <1 millimeter. The project will produce a new system for future installations, and for replacement of those in the field, at a low cost. The computer-controlled conveyor belt has the potential to be a critical unit in 30 percent of the systems installed in factories. The new system is also easier to update with future technologies.

The Project Priority Matrix for the Conveyor Belt Project (CBP) is:

Table Summary: Table has 4 columns. Column 1 has entries. Columns 2 to 4 titled Time, Scope and Cost respectively are indicated with X.

Time Scope Cost

Constrain X

EnhanceX

AcceptX

Table A2.9 has been developed for you to use in completing the project exercises.

TABLE A2.9 Conveyor Belt Project; WBS Table Summary: Table titled Conveyor Belt Project has 2 columns. Column 1 has 4 points. Column 2 has entries.

Conveyor Belt Project

Hardware Hardware specifications

Hardware design

Hardware documentation

Prototypes

Order circuit boards

Assemble preproduction models

Operating system Kernel specifications

Drivers

Disk drivers

Serial I/O drivers

Memory management

Operating system documentation

Network interface

Utilities Utilities specifications

Routine utilities

Complex utilities

Utilities documentation

Shell

System integration Architectural decisions

Integration first phase

System hard/software test

Project documentation

Integration acceptance testing

Assignment

Develop the WBS outline using the software available to you.

Question

Does this information (WBS) allow you to define any milestones of the project? Why or why not? What are they?

Remember: Save your file for future exercises!

Page 661

Part 2

Use your file from Part 1 and the information provided below to complete this exercise. (See Table A2.10.)

TABLE A2.10 Conveyor Belt Project; Schedule Table Summary: Table showing a Conveyor Belt Project; Schedule has 5 columns. Column 1 titled Activity lists numbers. Columns 2 and 3 titled Description and Resource respectively have entries. Column 4 titled Duration (days) has numbers. Column 5 titled Preceding Activity has numbers and 17F-S, lag 50 days.

Activity Description Resource Duration (days) Preceding Activity

1 Architectural decisions Design 25 —

2 Hardware specifications Design, Development 50 1

3 Kernel specifications Design 20 1

4 Utilities specifications Design, Development 15 1

5 Hardware design Design, Development 70 2

6 Disk drivers Assembly/test, Development 100 3

7 Memory management Development 0 3

8 Operating system documentation Design, Documentation 25 3

9 Routine utilities Development 60 4

10 Complex utilities Development 80 4

11 Utilities documentation Design, Development 20 4

12 Hardware documentation Design, Development 30 5

13 Integration first phase Assembly/test, Development 50 6, 7, 8, 9, 10, 11, 12

14 Prototypes Assembly/test, Development 80 13

15 Serial I/O drivers Development 130 13

16 System hard/software test Assembly/test 25 14, 15

17 Order circuit boards Purchasing 5 16

18 Network interface Development 90 16

19 Shell Development 60 16

20 Project documentation Development, Documentation 50 16

21 Assemble preproduction models Assembly/test, Development 30 17F-S, lag 50 days

22 Integrated acceptance testing Assembly/test, Development 60 18, 19, 20, 21

Note: F-S refers to a Finish-to-Start lag.

Each work package will represent an activity.

The project begins January 5, 2026.

The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (fourth Thursday in November), December 25.

If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off.

The project teams work eight-hour days, Monday through Friday.

Warning: Experience has taught students to frequently make separate backup files for each exercise. The software is never as friendly as users expect!

Construct a network schedule for the conveyor belt project and prepare a memo that addresses the following questions:

When is the project estimated to be completed? How long will the project take?

What is the critical path(s) for the project?

Which activity has the greatest amount of slack?

How sensitive is this network?

Identify two sensible milestones and explain your choices.

Compare the advantages/disadvantages of displaying the schedule as a network versus a Gantt chart.

Page 662

Include the following printouts:

A Gantt chart.

A network diagram highlighting the critical path.

A schedule table reporting ES, LS, EF, LF, and slack for each activity.

Hint: The project should be completed in 530 days.

Remember: Save your file for future exercises!

Part 3

Remember the old saying, “A project plan is not a schedule until resources are committed.” This exercise illustrates this subtle, but very important, difference.

Part A

Using your files from Part 2 input resources and their costs if you have not already done so. All information is found in Tables A2.10 and A2.11.

TABLE A2.11 Organization Resources Table Summary: Table showing an Organization Resources has 3 columns. Column 1 titled Name lists names. Column 2 titled Group lists groups. Column 3 titled Cost ($/hr) has dollar amounts.

Name Group Cost ($/hr)

Design R&D (2 teams) $100

Development R&D (2 teams) 70

Documentation R&D (1 team) 60

Assembly/test R&D (1 team) 70

Purchasing Procurement (1 team) 40

Prepare a memo that addresses the following questions:

Which if any of the resources are overallocated?

Assume that the project is time constrained and try to resolve any overallocation problems by leveling within slack. What happens?

What is the impact of leveling within slack on the sensitivity of the network?

Include a Gantt chart with the schedule table after leveling within slack.

Assume the project is resource constrained and resolve any overallocation problems by leveling outside of slack. What happens? What are the managerial implications?

What options are available at this point in time?

Include a Gantt chart with the schedule table after leveling outside of slack.

Note: No splitting of activities is allowed.

Note: No partial assignments (e.g., 50 percent). All resources must be assigned 100 percent.

Part B

When you show the resource-constrained network to top management, they are visibly shaken. After some explanation and negotiation they make the following compromise with you:

The project must be completed no later than February 1, 2028 (530 days).

You may assign two additional development teams.

If this does not suffice, you may hire other development teams from the outside. Hire as few external teams as possible because they cost $50 more per hour than your inside development people.

Page 663

Internal Development

Add as many development units (teams) as needed to stay within the 530 days. If you need more than two internal development units, then hire as few external teams as necessary. Select the cheapest possibility! Change as few activities as possible. It is recommended you keep work packages that require cooperation of several organizational units inside your company. You decide how best to do this.

Hint: Undo leveling prior to adding new resources.

Once you have obtained a schedule that meets the time and resource constraints, prepare a memo that addresses the following questions:

What changes did you make and why?

How long will the project take?

How did these changes affect the sensitivity of the network?

Include a Gantt chart with a schedule table presenting the new schedule.

Part 4

Based on the file created at the end of Part 3, prepare a memo that addresses the following questions:

How much will the project cost?

What does the cash flow statement tell you about how costs are distributed over the life span of the project?

Include a monthly cash flow and a cost table for the project.

Once you are confident that you have the final schedule, save the file as a baseline.

Hint: Save a backup file just in case without baseline!