Draw the activity on node network for the following project activities:
Activity Duration IPA
A 5 days –
B 3 days A
C 4 days A
D 5 days A
E 2 days B
F 3 days B, C
G 2 days D, E, F
Please submit your completed assignment using a format that adequately captures your hand-drawn network to the Week 1 weekly Assignment link. If you do not wish to submit a hand-drawn network diagram, you may use software to draw the diagram.