Budget Completion Ratio at End of Period Project Management Analysis

Overview

c9f6bd6a86ae1e6017ed3f1fThe chart shows four tasks (A, B, C, D), their dependencies, their durations, and their respective budgets.

Assume that:

The numbers shown above are weeks (not days as labeled incorrectly). For example, Task A has a duration of 16-weeks at cost $54,000.

You monitor the progress of the project every 4-weeks, i.e. at the end of Week 4 (EoW#4), 8, 12, 16, 20 and 24.

a.(6pts) Compute the PROJECT BUDGET, aka PV at the EoW#4, #8, #12, #16, #20, #24.

Hints:

i.Assume that budget per week is proportional to the duration of a task. For example, the budget at the end of week 1 for Task A is 1/16 of $54,000.

ii.Your PV must be cumulative, i.e. at the end of the 24th week, the total budget should be $105,000

iii.You must explain your calculations/logic in this WORD file, at least for EoW#4 and EoW#8.

iv.You must enter these data to an Excel spreadsheet as the PV row (or column) – zero credit if not.

b.(5pts) Assume that the project was completed perfectly on-time. Compute the Earned Value at the EoW#4, #8, #12, #16, #20, #24, following the 50-50 rules.

Hints:

i.You must explain your calculations/logic in this WORD file, at least for EoW#4 and EoW#8.

ii.You must enter these data to an Excel spreadsheet as the EV50 row – zero credit if not.

c.(5pts) Compute the Earned Value at the EoW#4, #8, #12, #16, #20, #24, following the 0-100 rules.

Hints:

iii.You must explain your calculations/logic in this WORD file, at least for EoW#4 and EoW#8.

iv.You must enter these data to an Excel spreadsheet as the EV100 row (or column) 

d.(9pts) Create a chart with the values of (a), (b) and (v). The horizontal axis must be the EoW#4, #8, #12, #16, #20, #24 weeks. This chart must be “cut-and-paste” in this WORD file.